What the Future Homes Standard actually costs developers

Our founder, Saghir Hussain, has written for PBC Today on why the deadline that decides a building's fate is earlier than most developers think, and where the cost really sits.

PBC TODAY · NOVEMBER 2026

Every housebuilder knows the date. The Future Homes Standard comes into force on 24 March 2027. What far fewer know is the date that actually decides whether a particular building is caught, and that is the date worth planning around.

The transition runs on two limbs. To stay on the old standards, the building notice, initial notice or full plans application for that building has to be with the local authority before 24 March 2027. Then work on that building has to have commenced before 24 March 2028. Miss either limb and the new rules apply.


The second limb is where it bites. "Commenced" is not a generous word. Under regulation 46A, for an ordinary building it means the sub-surface structure is finished: foundations in, any basement formed, and the structure of the ground floor complete. A trench dug or piling begun does not count. The ground floor structure has to be up.

And it applies per building, not per site. This is the part developers keep getting wrong. An early application does not throw a blanket over a whole scheme. Each building has to make its own start, in time, on its own. We have seen programmes where phase one sat comfortably inside the old regime and the later phases quietly slipped into the new one because nobody had mapped them individually.


The standard itself is often described as a fabric upgrade. It is more like a package. The notional building includes a heat pump instead of a gas boiler, waste water heat recovery, tighter airtightness and decentralised mechanical extract ventilation, with on-site renewables in most cases. Compliance moves to the Home Energy Model, running alongside SAP for a while. On their own, none of those is dramatic. Together, they change the shape of a house.


Most of the cost argument lands on the heat pump, because that is the visible change. In our experience, the money is decided much earlier. Form factor and orientation set how much energy a house loses long before anyone picks a boiler. Glazing ratios drive heat loss and, more and more, summertime overheating. Plant needs room to work: a cylinder, somewhere sensible for the heat pump, and a ventilation route that suits the plan rather than fights it. Thermal bridging is designed into the junction details long before it is built out.


Get those right at concept stage and the standard is mostly a specification exercise. Get them wrong and you are fitting compliance into a design that is already fixed. That is where it gets expensive.


The government's own assessment makes the point better than we can. The impact assessment published with the standard found that retrofitting a home to a Future Homes Standard equivalent costs around 66 to 80 per cent more than building to it during construction. That gap is the real cost of the standard. It is the sequence of decisions that drives it, not the kit.

If you have plots that will not make the transition, the useful work is dull and specific. Map every building against both dates: application in before 24 March 2027, sub-structure complete before 24 March 2028. Miss the window for a building and it meets the full standard, whether or not the rest of the scheme does. Any plot whose programme has the ground floor slab landing in early 2028 is a plot at risk, and it is worth a look now, while the programme can still move.


For those plots, model the compliant scheme instead of assuming it. Fabric, thermal bridging and the renewables requirement all move together, and the cheapest time to find out what they add is before the house types are frozen. Once the drawings are issued and the site is running, the same answer costs a lot more to act on.


The pre-March rush deserves some caution too. Plenty of developers are lodging applications ahead of 2027 to hold on to the old standard, and the impact assessment expects exactly that. It works, but only if the second limb is honoured, and only building by building. An application that protects the first two houses of a 30-house scheme has not protected much.


None of this is an argument against the standard. A home designed to it is better than one bolted on to it, and the occupier's running costs show it. It is an argument about sequence. The developers who get through the next 18 months well will be the ones who treated March 2027 as a design deadline rather than a construction one, and found out what compliance would cost while it was still cheap to change their minds.

Read the full article in PBC Today:

https://www.pbctoday.co.uk/news/publication/pbc-today-november-2026/167304/

Read it in the digital edition (page 62):

https://edition.pagesuite-professional.co.uk/html5/reader/production/default.aspx?pubname=&edid=7a863e93-10fd-4287-99a1-22186d9e2ccc&pnum=8


Frequently Asked Questions

When does the Future Homes Standard come into force?

24 March 2027 for ordinary building work in England. Buildings that meet the transition rules stay on the previous standards.

What are the two transition deadlines?

The application must be with the local authority before 24 March 2027, and work on that building must have commenced before 24 March 2028. Both limbs have to be met. Missing either one means the new standard applies.

What counts as "commenced" under the regulations?

For an ordinary building, the sub-surface structure must be finished: foundations in, any basement formed, and the ground floor structure complete. A trench or piling alone does not count.

Does an early application protect the whole site?

No. The transition applies per building, not per site. Each building has to make its own start, in time. An early application on the first phase does not cover later phases.

Why is it cheaper to design to the standard than to retrofit?

The government's impact assessment puts the cost of retrofitting at around 66 to 80 per cent more than building to the standard from the start. The main cost driver is the sequence: form, orientation, glazing and plant space are fixed at concept stage, and changing them later is expensive.

What should a developer do now?

Map every building against both dates, identify the plots whose ground floor slab lands in early 2028, and model the compliant scheme before the house types are frozen. The earlier that work happens, the cheaper it is to act on.

Where can I read the full article?

It is published in PBC Today, November 2026, pages 62 to 63. The online version is at https://www.pbctoday.co.uk/news/publication/pbc-today-november-2026/167304/.